They’ve been working hard on our new church building since the last update. We have solid ground (more than 100 loads of fill brought in) and the beginnings of some walls.
Worked has slowed because we don’t have permitting completed yet. We had special permission to deal with the drainage issues while in the permitting process.
How you cross the ditch to get onto the site. It’s quite sturdy.
Facing northeast.
Facing south.
The new western wall.
The beginnings of a wall! (Between the sanctuary and narthex.)
Ross is checking out the area where he’ll be preaching from.
Lots of holes.
This is a sort of ravine. The water drains off the property here.
The only remaining wall from the original building. It still has an evacuation route notice.
The lake-side part of the west wall.